On Tue, Oct 07, 2025 at 12:27:16PM +0200, Patrick Steinhardt wrote:
Show 7 quoted lines
> Yeah, it's definitely my goal here to do exactly that: reach out to > folks and take everyone's input into account. Once we've got it, propose > a timeline. > > I guess as part of that initial communication with the stakeholders we > can also mention that the current plan is to release roughly towards the > end of next year, which may help to put things into perspective.
I am not sure what our proposal would be other than max(proposed_dates), clamped to some reasonable range that we are comfortable with so as not to delay the transition to use SHA-256 by default too far into the future.
I think a more interesting question is:
- What do we do for implementations that do not have a roadmap, or whose roadmap is too far into the future?
- What do we do for implementations that have a roadmap, have a date that is palatable to the project, but end up slipping and are unable to meet that date?
I generally agree that we have to draw a line in the sand *somewhere*, but I don't think we should be so inflexible as to say "if you don't have SHA-256 done by X date, you are out of luck". Of course, if the amended timeline is too far beyond the initial deadline that's one case. But if someone is a release cycle or so behind, I think it's reasonable that the project should be flexible enough to accommodate that.
Thanks, Taylor