Re: Let's make our cycles shorter
- From
Junio C Hamano <gitster@pobox.com>
- Date
- Apr 25, 2011, 17:03 UTC
- Message-ID
- <7v1v0ql0uw.fsf@alter.siamese.dyndns.org>
- In-Reply-To
- <BANLkTinzXLK0dHYjBMpBgLqZ_7KNHeu3uA@mail.gmail.com>
Sebastien Douche <sdouche@gmail.com> writes:
> On Fri, Apr 1, 2011 at 00:35, Junio C Hamano <gitster@pobox.com> wrote: > ... > I was surprised to not read response, it's having sensitive impact on > the project.
Hmm, what sensitive impact on which project do you have in mind?
> Junio, it's effective now?
The structure of clean-up, development, freeze and then release has always been in effect in this project, but historically the duration of the development stretch varied a lot from cycle to cycle.
I just spelled the structure out for the next cycle, and tried to give some predictable bounds to that elastic development stretch, in order to force myself to stick to a schedule in which we can make measurable progress in reasonable amount of time.
It does not mean that we won't be tackling issues that will take more than N weeks to perfect. Either a topic gets polished enough in a single cycle to graduate to 'master' before -rc0, or it keeps cooking in 'next' during the feature freeze, and will attempt to be in the release after that.
I've tentatively set the following dates on my calendar, based on 9-week cycle:
- Today is the beginning of week #1 for this cycle.
- The entire month of May 2011 will be the development stretch (lasting up to Week #5 that ends May 29th).
- Aim to tag 1.7.6-rc0 on June 1st, 2011, -rc1 on 8th, -rc2 on 15th.
- Either tag 1.7.6 final on 19th or have -rc3 on 22nd and final on 26th of June.
If you happen to use Google Calendar, you can paste:
jfgbl2mrlipp4pb6ieih0qr3so@group.calendar.google.com